[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109490":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109490,783,1,"单选题","关于施工合同履行过程中暂估价的确定，下列说法中正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不属于依法必须招标的材料，以承包人自行采购的价格取代暂估价",false,{"key":16,"text":17,"correct":18},"B","属于依法必须招标的暂估价设备，由发承包双方以招标方式选择供应商，以中标价取代暂估价",true,{"key":20,"text":21,"correct":14},"C","不属于依法必须招标的暂估价专业工程，不应按工程变更确定价款而应另行签订补充协议确定工程价款",{"key":23,"text":24,"correct":14},"D","属于依法必须招标的暂估价专业工程，承包人不得参加投标","暂估材料或工程设备的单价确定后，在综合单价中只应取代原暂估单价，不应再在综合单价中涉及企业管理费或利润等其他费的变动。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]