[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109489":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109489,783,1,"单选题","发包人在招标工程量清单中给定某工程设备暂估价，下列关于该工程设备价款调整的说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","依法可不招标的项目，应由发包人组织采购，以采购价格取代暂估价",false,{"key":16,"text":17,"correct":18},"B","依法可不招标的项目，应由承包人按合同约定采购，以发包人确认后的价格取代暂估价",true,{"key":20,"text":21,"correct":14},"C","依法必须招标的项目，应由发包人招标选择供应商，以中标价格取代暂估价",{"key":23,"text":24,"correct":14},"D","依法必须招标的项目，应由承包人招标选择供应商，以中标价格取代暂估价","本题考查的是暂估价。非必须招标，承包人采购，发包人确认后取代暂估价，调整合同价款；必须招标，双方以招标的方式选择供应商。中标价格取代暂估价，调整合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]