[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109487":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109487,783,1,"单选题","2010 年3 月，实际完成的某工程基准日期的价格为1500 万元。调值公式中的固定系数为0.3，相关成本要素中，水泥的价格指数上升了20%，水泥的费用占合同调值部分的40%，其它成本要素的价格均未发生变化。2010 年3 月应调整的合同价的差额为()万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","84",true,{"key":16,"text":17,"correct":18},"B","126",false,{"key":20,"text":21,"correct":18},"C","1584",{"key":23,"text":24,"correct":18},"D","1626","固定系数为O.3,合同调值部分为O.7,水泥的费用占合同调值部分的40%,即占合同的O.7×40%=0.28,其它材料占合同的O.7×60%=0.42。 应调整合同价差额=1500×[0.3+(1+20%)×0.28+0.42-1]=1500×20%×0.28=84 万元。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]