[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109486":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109486,783,1,"单选题","根据《建设工程工程量清单计价规范》，某工程定额工期为25个月，合同工期为20个月。合同实施中，发包人要求该工程提前1个月竣工，征得承包人同意后，调整了合同工期。则关于该工程工期和赶工费用的说法，正确的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人要求合同工期比定额工期提前6个月竣工，应承担提前竣工6个月的赶工费用",false,{"key":16,"text":17,"correct":18},"B","发包人要求合同工程提前1个月竣工，应承担提前竣工1个月的赶工费用",true,{"key":20,"text":21,"correct":14},"C","发包人要求压缩的工期天数超过定额工期的20%，应承担提前竣工5个月的赶工费用",{"key":23,"text":24,"correct":14},"D","发包人要求压缩的工期天数未超过定额工期的30%，不支付赶工费用","工程发包时，招标人应当依据相关工程的工期定额合理计算工期，压缩的工期天数不得超过定额工期的20%，将其量化。超过者，应在招标文件中明示增加赶工费用。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]