[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109477":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109477,783,1,"单选题","《建设工程工程量清单计价规范》GB50500—2013对计日工生效计价的原则做出了规定：发包人在收到承包人提交现场签证报告后的（ ）内予以确认并将其中一份返还给承包人，作为计日工计价和支付的依据。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1天",false,{"key":16,"text":17,"correct":18},"B","2天",true,{"key":20,"text":21,"correct":14},"C","5天",{"key":23,"text":24,"correct":14},"D","7天","2020教材P166-167 《建设工程工程量清单计价规范》GB 50500—2013对计日工生效计价的原则做了以下规定：任一计日工项目持续进行时，承包人应在该项工作实施结束后的24h内向发包人提交有计日工记录汇总的现场签证报告一式三份。发包人在收到承包人提交现场签证报告后的2天内予以确认并将其中一份返还给承包人，作为计日工计价和支付的依据。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]