[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109475":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109475,783,1,"单选题","某混凝土结构工程，工程量清单中估计工程量为3000m3，合同规定混凝土结构工程综合单价为550元／m3，实际工程量超过估计工程量15％以上时，超过部分单价下调10％，工程结束时承包人实际完成混凝土结构工程量为3300m3，则该项工程结算款为（）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","163.4",false,{"key":16,"text":17,"correct":14},"B","165.0",{"key":19,"text":20,"correct":21},"C","181.5",true,{"key":23,"text":24,"correct":14},"D","199.7","2020教材P164-166 该工程的工程量偏差为不足15％，即3300\u003C3000(1+15％)=3450。故执行原单价，该项工程结算款为3300×550=181.5(万元)。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]