[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109474":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109474,783,1,"单选题","下列合同价款调整因素的类别中，现场签证属于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","物价变化类",false,{"key":16,"text":17,"correct":14},"B","法规变化类",{"key":19,"text":20,"correct":14},"C","工程变更类",{"key":22,"text":23,"correct":24},"D","其他类",true,"2020教材P163-164 《建设工程工程量清单计价规范》GB 50500—2013参照国内外多部合同范本，结合工程建设合同的实践经验和建筑市场的交易习惯，对所有涉及合同价款调整、变动的因素或其范围进行了归并，主要包括五大类：一是法规变化类(法律法规变化)；二是工程变更类(工程变更、项目特征不符、工程量清单缺项、工程量偏差、计日工)；三是物价变化类(物价变化、暂估价)；四是工程索赔类(不可抗力、提前竣工、索赔等)；五是其他类(现场签证等)。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]