[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109465":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109465,783,1,"单选题","关于单价合同中工程计算的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单价合同应予计量的工程量是承包人实际施工的工程量",false,{"key":16,"text":17,"correct":14},"B","承包人因自身原因造成返工的工程量应予计量",{"key":19,"text":20,"correct":21},"C","工程计量应以设计图纸为依据",true,{"key":23,"text":24,"correct":14},"D","承包人为保证工程质量超过图纸要求的工程量应予计量","工程量必须以承包人完成合同工程应予计量的工程量确定。计量的几何尺寸要以设计图纸为依据，工程师对承包人超出设计图纸要求增加的工程量和自身原因造成返工的工程量，不予计量。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]