[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109429":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109429,783,1,"单选题","某工程施工过程中，监理工程师要求承包单位在工程施工之前根据施工过程质量控制的要求提交质量控制点明细表并实施质量控制，这是（ ）的原则要求。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","坚持质量第一",false,{"key":16,"text":17,"correct":14},"B","坚持质量标准",{"key":19,"text":20,"correct":21},"C","坚持预防为主",true,{"key":23,"text":24,"correct":14},"D","坚持科学的职业道德规范","考点:工程质量控制的原则。工程质量控制应该是积极主动的，应事先对影响质量的各种因素加以控制，而不能是消极被动的。以预防为主，加强过程和中间产品的质量检查和控制。参见教材P5。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]