[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109427":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109427,783,1,"单选题","涉及建筑主体变动或承重结构变动的装修工程，应由（ ）在施工前委托原设计单位提出设计方案，并经相关单位审批后方可施工。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","监理单位",false,{"key":16,"text":17,"correct":14},"B","装修施工单位",{"key":19,"text":20,"correct":14},"C","工程质量监督机构",{"key":22,"text":23,"correct":24},"D","建设单位",true,"考点:工程参建各方的质量责任和义务。涉及建筑主体和承重结构变动的装修工程，建设单位应在施工前委托原设计单位或者相应资质等级的设计单位提出设计方案；没有设计方案的，不得施工。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]