[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109407":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109407,783,1,"单选题","施工阶段质量控制是工程项目全过程质量控制的关键环节，其工作重点应是（ ）控制。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","事前",false,{"key":16,"text":17,"correct":14},"B","事中",{"key":19,"text":20,"correct":14},"C","事后",{"key":22,"text":23,"correct":24},"D","事前和事中",true,"2020版教材P5 本题考查的是工程质量形成过程与影响因素。工程质量控制应该是积极主动的，应事先对质量的各种影响因素加以控制，要重点做好质量的事先控制和事中控制，以预防为主，加强过程和中间产品的质量检查和控制。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]