[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109399":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109399,783,1,"单选题","（）的质量控制，主要是通过项目的可行性研究，选择最佳建设方案，使项目的质量要求符合业主的意图，并与投资目标相协调，与所在地区环境相协调。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程设计阶段",false,{"key":16,"text":17,"correct":14},"B","施工控制阶段",{"key":19,"text":20,"correct":14},"C","工程勘察阶段",{"key":22,"text":23,"correct":24},"D","决策阶段",true,"2020教材P4 决策阶段的质量控制，主要是通过项目的可行性研究，选择最佳建设方案，使项目的质量要求符合业主的意图，并与投资目标相协调，与所在地区环境相协调。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]