[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109390":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109390,783,1,"单选题","工程质量形成过程中，直接影响项目决策和设计质量的是（ ）阶段。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","勘察设计",false,{"key":16,"text":17,"correct":18},"B","可行性研究",true,{"key":20,"text":21,"correct":14},"C","竣工验收",{"key":23,"text":24,"correct":14},"D","施工安装","2020版教材P2-3 项目可行性研究需要确定工程项目的质量要求，并与投资目标相协调。因此，项目的可行性研究直接影响项目的决策质量和设计质量。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]