[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109389":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109389,783,1,"单选题","工程质量控制应该是积极主动的，要重点做好质量的（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","事前控制",false,{"key":16,"text":17,"correct":14},"B","事中控制",{"key":19,"text":20,"correct":14},"C","事后控制",{"key":22,"text":23,"correct":24},"D","事前控制和事中控制",true,"2020版教材P4-5 工程质量控制应该是积极主动的，应事先对影响质量的各种因素加以控制，而不能是消极被动的，等出现质量问题再进行处理，以免造成不必要的损失。所以，要重点做好质量的事前控制和事中控制，以预防为主，加强过程和中间产品的质量检查和控制。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]