[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109387":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109387,783,1,"单选题","工程建设的不同阶段，对工程项目质量的形成起着不同的作用和影响。其中项目决策阶段是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","将项目质量目标和水平具体化",false,{"key":16,"text":17,"correct":18},"B","确定项目应达到的质量目标与水平",true,{"key":20,"text":21,"correct":14},"C","将项目质量目标和制度具体化",{"key":23,"text":24,"correct":14},"D","确定项目应达到的质量目标与制度","2020版教材P2-3 项目决策阶段是通过项目可行性研究和项目评估，对项目的建设方案做出决策，使项目的建设充分反映业主的意愿，并与地区环境相适应，做到投资、质量、进度三者协调统一。所以，项目决策阶段对工程质量的影响主要是确定工程项目应达到的质量目标和水平。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]