[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109381":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109381,783,1,"单选题","下列关于建设单位的质量责任，叙述错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位不得迫使承包方以低于成本的价格竞标",false,{"key":16,"text":17,"correct":14},"B","建设单位不得任意压缩合理工期",{"key":19,"text":20,"correct":14},"C","建设单位不得明示或者暗示施工单位违反工程建设强制性标准，降低建设工程质量",{"key":22,"text":23,"correct":24},"D","建设单位可以根据工程的具体情况决定是否采取招标",true,"2020版教材P11-12 建设工程发包时，不得迫使承包方以低于成本的价格竞标，不得任意压缩合理工期。不得明示或者暗示设计单位或者施工单位违反工程建设强制性标准，降低建设工程质量。应当依法对工程建设项目的勘察、设计、施工、监理以及与工程建设有关的重要设备、材料等的采购进行招标。故选项D说法错误，符合题意。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]