[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109374":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109374,783,1,"单选题","建设单位应当自领取施工许可证之日起（ ）个月内开工，因故不能按期开工的，应当向发证机关延期申请；延期以（ ）次为限，每次不超过（ ）个月。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1,1,1",false,{"key":16,"text":17,"correct":14},"B","2,2,2",{"key":19,"text":20,"correct":14},"C","3,3,3",{"key":22,"text":23,"correct":24},"D","3,2,3",true,"建设单位应当自领取施工许可证之日起3个月内开工。因故不能按期开工的，应当向发证机关申请延期；延期以两次为限，每次不超过3个月。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]