[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109345":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109345,783,1,"单选题","下列不属于工程勘察设计阶段的质量控制的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","选择好勘察设计单位",false,{"key":16,"text":17,"correct":14},"B","保证工程设计符合决策阶段确定的质量要求",{"key":19,"text":20,"correct":14},"C","保证设计符合有关技术规范和标准的规定",{"key":22,"text":23,"correct":24},"D","择优选择服务质量好的监理单位",true,"2020版教材P4 工程勘察设计阶段的质量控制，主要是要选择好勘察设计单位，要保证工程设计符合决策阶段确定的质量要求，保证设计符合有关技术规范和标准的规定，要保证设计文件、图纸符合现场和施工的实际条件，其深度能满足施工的需要。 选项D“择优选择服务质量好的监理单位”属于工程施工阶段的质量控制，故符合题意要求。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]