[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109344":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109344,783,1,"单选题","某工程施工过程中，监理工程师要求承包单位在工程施工之前，根据施工过程质量控制的要求，提交质量控制点明细表，并实施质量控制，这是（ ）的原则要求。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","坚持质量第一",false,{"key":16,"text":17,"correct":14},"B","坚持质量标准",{"key":19,"text":20,"correct":21},"C","坚持预防为主",true,{"key":23,"text":24,"correct":14},"D","坚持科学的职业道德规范","2020版教材P4-5 坚持预防为主的原则 工程质量控制应该是积极主动的，应事先对影响质量的各种因素加以控制，而不能是消极被动的，等出现质量问题再进行处理，已造成不必要的损失，所以，要重点做好质量的事前控制和事中控制，以预防为主，加强过程和中间产品的质量检查和控制。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]