[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109330":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109330,783,1,"单选题","通过项目可行性研究和项目评估，对项目的建设方案做出决策，使项目的建设充分反映业主的意愿，该阶段指的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程勘察设计阶段",false,{"key":16,"text":17,"correct":14},"B","工程施工阶段",{"key":19,"text":20,"correct":21},"C","项目决策阶段",true,{"key":23,"text":24,"correct":14},"D","项目可行性研究阶段","2020版教材P2-3 项目决策阶段是通过项目可行性研究和项目评估，对项目的建设方案做出决策，使项目的建设充分反映业主的意愿，并与地区环境相适应，做到投资、质量、进度三者协调统一。所以，项目决策阶段对工程质量的影响主要是确定工程项目应达到的质量目标和水平。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]