[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109320":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109320,783,1,"单选题","（2020年真题）根据《建筑工程施工质量验收统一标准》，负责组织分项工程验收的人员是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专业监理工程师",true,{"key":16,"text":17,"correct":18},"B","施工单位项目技术负责人",false,{"key":20,"text":21,"correct":18},"C","建设单位现场负责人",{"key":23,"text":24,"correct":18},"D","总监理工程师","P159-179 分项工程应由专业监理工程师组织施工单位项目专业技术负责人等进行验收。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]