[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109317":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109317,783,1,"单选题","（2019年真题）隐蔽工程为检验批时，隐蔽工程应由（ ）组织进行验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专业监理工程师",true,{"key":16,"text":17,"correct":18},"B","总监理工程师",false,{"key":20,"text":21,"correct":18},"C","施工单位项目负责人",{"key":23,"text":24,"correct":18},"D","建设单位项目负责人","本题考核的是隐蔽工程的验收。如隐蔽工程为检验批时，隐蔽工程应由专业监理工程师组织施工单位项目专业质量检查员、专业工长等进行验收。施工单位应对隐蔽工程质量进行自检，对存在的问题自行整改处理，合格后填写隐蔽工程报审、报验表及隐蔽工程质量验收记录，并将相关资料报送项目监理机构申请验收。专业监理工程师对施工单位所报资料进行审查，并组织相关人员到现场进行实体检查、验收。对验收不合格的，专业监理工程师应要求施工单位进行整改，自检合格后予以复验；对验收合格的，专业监理工程师应签认隐蔽工程报审、报验表及质量验收记录，准许进行下道工序施工。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]