[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109313":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109313,783,1,"单选题","（2019年真题）根据《建筑工程施工质量验收统一标准》GB 50300—2013，单位工程质量竣工验收记录表中验收结论由（ ）填写。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":18},"B","监理单位",true,{"key":20,"text":21,"correct":14},"C","施工单位",{"key":23,"text":24,"correct":14},"D","设计单位","本题考核的是单位工程质量竣工验收、检查记录的填写。单位工程质量竣工验收记录中的验收记录由施工单位填写，验收结论由监理单位填写；综合验收结论由参加验收各方共同商定，由建设单位填写，并应对工程质量是否符合设计和规范要求及总体质量水平作出评价。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]