[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109312":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109312,783,1,"单选题","（2019年真题）根据《建筑工程施工质量验收统一标准》GB 50300—2013，单位工程完工后，（ ）组织对工程质量进行竣工预验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专业监理工程师",false,{"key":16,"text":17,"correct":18},"B","总监理工程师",true,{"key":20,"text":21,"correct":14},"C","施工单位项目负责人",{"key":23,"text":24,"correct":14},"D","建设单位项目负责人","本题考核的是竣工预验收。单位工程完工后，施工单位应依据验收规范、设计图纸等组织有关人员进行自检，对存在的问题自行整改处理，合格后填写单位工程竣工验收报审表，并将相关竣工资料报送项目监理机构申请预验收。总 监理工程师应组织各专业监理工程师审查施工单位报送的相关竣工资料，并对工程质量进行竣工预验收。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]