[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109306":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109306,783,1,"单选题","（2018年真题）根据《建设工程监理规范》GB\u002FT 50319—2013，单位工程完工后，工程竣工预验收应由（ ）组织相关人员进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总监理工程师",true,{"key":16,"text":17,"correct":18},"B","建设单位项目负责人",false,{"key":20,"text":21,"correct":18},"C","总监理工程师代表",{"key":23,"text":24,"correct":18},"D","施工单位项目负责人","根据《建设工程监理规范》，总监理工程师应履行的职责中包括审查施工单位的竣工申请，组织工程竣工预验收，组织编写工程质量评估报告，参与工程竣工验收，并且该项职责不得委托给总监理工程师代表。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]