[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109304":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109304,783,1,"单选题","（2017年真题）经项目监理机构对竣工资料及工程实体预验收合格后，由总监理工程师签署工程竣工报验单并向建设单位提交（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理总结报告",false,{"key":16,"text":17,"correct":18},"B","质量评估报告",true,{"key":20,"text":21,"correct":14},"C","监理验收报告",{"key":23,"text":24,"correct":14},"D","质量检验报告","本题考查的是建筑工程施工质量验收程序和合格规定。总监理工程师应签认单位工程竣工验收的相关资料，项目监理机构应编写工程质量评估报告，并应经总监理工程师和工程监理单位技术负责人签字后报建设单位。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]