[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109281":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109281,783,1,"单选题","对验收合格的分部工程，（ ）签认分部工程报验表及验收记录。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总监理工程师",true,{"key":16,"text":17,"correct":18},"B","专业监理工程师",false,{"key":20,"text":21,"correct":18},"C","项目经理",{"key":23,"text":24,"correct":18},"D","项目专业技术负责人","2020版教材P159-179 总监理工程师组织相关人员进行检查、验收，对验收不合格的分部工程，要求施工单位进行整改，自检合格后予以复查。对验收合格的分部工程，应签认分部工程报验表及验收记录。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]