[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109274":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109274,783,1,"单选题","在工程施工质量验收层次中，检验批的划分依据不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程量",false,{"key":16,"text":17,"correct":18},"B","主要工种",true,{"key":20,"text":21,"correct":14},"C","施工段",{"key":23,"text":24,"correct":14},"D","变形缝","2020版教材P155-157 检验批可根据施工、质量控制和专业验收的需要，按工程量、楼层、施工段、变形缝进行划分。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]