[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109249":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109249,783,1,"单选题","下列关于工程施工质量验收不符合要求的处理，说法正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","经返工或返修的检验批，应协商后进行验收",false,{"key":16,"text":17,"correct":14},"B","有资质的检测机构和建设单位鉴定能够到达设计要求的检验批，予以验收",{"key":19,"text":20,"correct":14},"C","有资质的检测机构鉴定达不到设计要求，但经建设单位核算认可能够满足安全和使用功能的检验批，予以验收",{"key":22,"text":23,"correct":24},"D","工程质量控制资料应齐全完整",true,"2020版教材P180 选项A，经返工或返修的检验批，应重新进行验收。选项B，经有资质的检测机构检测鉴定能够到达设计要求的检验批，予以验收。选项C，经有资质的检测机构检测鉴定达不到设计要求，但经原设计单位核算认可能够满足安全和使用功能的检验批，予以验收。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]