[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109240":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109240,783,1,"单选题","关于分部工程观感质量验收的说法中，错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","只能以观察、触摸或简单量测的方式结合人的主观判断",false,{"key":16,"text":17,"correct":14},"B","综合评价“好”是指在观感质量符合验收规范的基础上，能到达精致、细部处理到位等要求",{"key":19,"text":20,"correct":14},"C","综合评价“一般”是指观感质量能符合验收规范的要求",{"key":22,"text":23,"correct":24},"D","综合评价“差”是指观感质量勉强达到验收规范要求，但影响安全或使用功能",true,"2020版教材P159-179 选项D，“差”是指观感质量勉强达到验收规范的要求，或有明显的缺陷，但不影响安全或使用功能。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]