[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109239":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109239,783,1,"单选题","单位工程的验收应由（ ）组织。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位项目负责人",true,{"key":16,"text":17,"correct":18},"B","总监理工程师",false,{"key":20,"text":21,"correct":18},"C","专业监理工程师",{"key":23,"text":24,"correct":18},"D","项目负责人","2020版教材P159-179 建设单位收到工程竣工报告后，由建设单位项目负责人组织监理、施工、设计、勘察等单位项目负责人进行单位工程验收。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]