[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109234":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109234,783,1,"单选题","分部工程应由（ ）组织相关人员进行验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总监理工程师",true,{"key":16,"text":17,"correct":18},"B","专业监理工程师",false,{"key":20,"text":21,"correct":18},"C","建设单位代表",{"key":23,"text":24,"correct":18},"D","施工项目经理","2020版教材P159-179 分部工程应由总监理工程师组织施工单位项目负责人和项目技术负责人等进行验收。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]