[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109222":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109222,783,1,"单选题","在工程施工质量验收中，为了更加科学地评价工程施工质量，按（ ）原则可将单位工程划分为若干个分部工程。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计图纸",false,{"key":16,"text":17,"correct":14},"B","重要程度",{"key":19,"text":20,"correct":14},"C","投资估算",{"key":22,"text":23,"correct":24},"D","结构分解",true,"2020版教材P155 为了更加科学地评价工程施工质量和有利于对其进行验收，根据工程特点，按结构分解的原则将单位或子单位工程又划分为若干个分部工程。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]