[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109206":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109206,783,1,"单选题","施工图设计评审的总体审核中，首先应审核（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工艺合理性",false,{"key":16,"text":17,"correct":18},"B","施工图纸的完整性及各级的签字盖章",true,{"key":20,"text":21,"correct":14},"C","总图在平面和空间布置上是否有交叉和矛盾",{"key":23,"text":24,"correct":14},"D","工艺流程及装置是否满足规范","2020版教材P100-102 总体审核。首先审核施工图纸的完整性及各级的签字盖章。其次要重点审核工艺和总图布置的合理性，项目是否齐全，有无遗漏项，总图在平面和空间布置上是否有交叉和矛盾；工艺流程及装置、设备是否满足标准、规程、规范等要求。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]