[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109193":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109193,783,1,"单选题","工程勘察工作的阶段划分不包括（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","选址勘察",false,{"key":16,"text":17,"correct":14},"B","初步勘察",{"key":19,"text":20,"correct":14},"C","详细勘察",{"key":22,"text":23,"correct":24},"D","决策性勘察",true,"2020版教材P95 工程勘察工作一般分三个阶段，即可行性研究勘察、初步勘察、详细勘察。可行性研究勘察，又称选址勘察。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]