[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109188,783,1,"单选题","（2019年真题）工程施工工期应自（ ）中载明的开工日期起计算。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程开工报审表",false,{"key":16,"text":17,"correct":14},"B","施工组织设计报审表",{"key":19,"text":20,"correct":14},"C","施工控制测量成果报验表",{"key":22,"text":23,"correct":24},"D","工程开工令",true,"本题考查的是现场施工准备的质量控制。总监理工程师应在开工日期7天前向施工单位发出工程开工令。工期自总监理工程师发出的工程开工令中载明的开工日期起计算。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]