[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109178":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109178,783,1,"单选题","（2018年真题）工程开工前，应由（ ）组织召开工程设计技术交底会议。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计单位",false,{"key":16,"text":17,"correct":14},"B","施工单位",{"key":19,"text":20,"correct":21},"C","建设单位",true,{"key":23,"text":24,"correct":14},"D","监理单位","本题考查的是图纸会审与设计交底。工程开工前，建设单位应组织并主持召开工程设计技术交底会",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]