[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109175":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109175,783,1,"单选题","（2017年真题）总监理工程师应在工程开工日期（ ）天前向施工单位发出工程开工令。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":18},"B","7",true,{"key":20,"text":21,"correct":14},"C","10",{"key":23,"text":24,"correct":14},"D","14","总监理工程师应在开工日期7天前向施工单位发出工程开工令。工期自总监理工程师发出的工程开工令中载明的开工日期起计算。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]