[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109170":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109170,783,1,"单选题","（2017年真题）根据《建设工程监理规范》GB\u002FT 50319—2013，项目监理机构应根据工程特点和（ ）确定需要旁站的关键部位、关键工序。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理实施细则",false,{"key":16,"text":17,"correct":18},"B","施工组织设计",true,{"key":20,"text":21,"correct":14},"C","监理规划",{"key":23,"text":24,"correct":14},"D","设计图纸","旁站工作程序： ①开工前，项目监理机构应根据工程特点和施工单位报送的施工组织设计，确定旁站的关键部 位、关键工序，并书面通知施工单位； ②施工单位在需要实施旁站的关键部位、关键工序进行施工前书面通知项目监理 机构； ③接到施工单位书面通知后，项目机构应安排旁站监理人员实施旁站。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]