[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109162":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109162,783,1,"单选题","（2016年真题）建设单位负责采购的主要设备进场后，应由（ ）三方共同进行开箱检查。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设单位、供货单位、施工单位",false,{"key":16,"text":17,"correct":14},"B","供货单位、施工单位、项目监理机构",{"key":19,"text":20,"correct":21},"C","建设单位、施工单位、项目监理机构",true,{"key":23,"text":24,"correct":14},"D","供货单位、设计单位、施工单位","由建设单位采购的主要设备则由建设单位、施工单位、项目监理机构进行开箱检查，并由三方在开箱检查记录上 签字",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]