[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109159":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109159,783,1,"单选题","（2015年真题）涉及工程设计文件修改的工程变更，应由（ ）转交原设计单位修改工程设计文件。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目监理机构",false,{"key":16,"text":17,"correct":14},"B","施工单位技术负责人",{"key":19,"text":20,"correct":14},"C","施工单位项目负责人",{"key":22,"text":23,"correct":24},"D","建设单位",true,"本题考查的是工程变更的控制。当施工单位提出的工程变更要求对设计图纸和设计文件所表达的设计标准、状态有改变或修改时，项目监理机构经与建设单位、设计单位、施工单位研究并做出变更决定后，由建设单位转交原设计单位修改工程设计文件，再由总监理工程师签发工程变更单，并附设计单位提交的修改后的工程设计图纸交施工单位按变更后的图纸施工。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]