[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109148":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109148,783,1,"单选题","用于钢结构安装等满堂支撑体系，承受单点集中荷载（ ）及以上，属于超过一定规模的危险性较大的分部分项工程。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3KN",false,{"key":16,"text":17,"correct":14},"B","5KN",{"key":19,"text":20,"correct":21},"C","7KN",true,{"key":23,"text":24,"correct":14},"D","9KN","2020版教材P149-150 模板工程及支撑体系 (1)各类工具式模板工程：包括滑模、爬模、飞模、隧道模等工程。 (2)混凝土模板支撑工程：搭设高度8m 及以上；搭设跨度18m及以上；施工总荷载(设计值) 15kN\u002Fm2及以上；或集中线荷载(设计值) 20kN\u002Fm 及以上。 (3)承重支撑体系：用于钢结构安装等满堂支撑体系，承受单点集中荷载7kN 及以上。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]