[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109143":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109143,783,1,"单选题","对于施工单位提出的工程变更，（）组织建设单位、施工单位等共同协商确定工程变更费用及工期变化，会签工程变更单。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位负责人",false,{"key":16,"text":17,"correct":14},"B","建设单位技术负责人",{"key":19,"text":20,"correct":14},"C","专业监理工程师",{"key":22,"text":23,"correct":24},"D","总监理工程师",true,"2020版教材P144-145 对于施工单位提出的工程变更，总监理工程师组织建设单位、施工单位等共同协商确定工程变更费用及工期变化，会签工程变更单。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]