[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109140":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109140,783,1,"单选题","施工图设计文件审查合格后，（）应及时主持召开图纸会审会议，与会各方会签会议纪要。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","施工单位",false,{"key":20,"text":21,"correct":18},"C","项目监理机构",{"key":23,"text":24,"correct":18},"D","设计单位","2020版教材P108-109 本题考查的是图纸会审与设计交底。建设单位应及时主持召开图纸会审会议，组织项目监理机构、施工单位等相关人员进行图纸会审，并整理成会审问题清单，由建设单位在设计交底前约定的时间内提交设计单位。图纸会审由施工单位整理会议纪要，与会各方会签。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]