[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109133":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109133,783,1,"单选题","通常情况下，施工方案应由（ ）组织编制，并经（ ）审批签字后提交项目监理机构。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目经理；项目技术负责人",false,{"key":16,"text":17,"correct":14},"B","项目经理；施工单位技术负责人",{"key":19,"text":20,"correct":21},"C","项目技术负责人；施工单位技术负责人",true,{"key":23,"text":24,"correct":14},"D","项目技术负责人；施工单位项目负责人","2020版教材P112 通常情况下，施工方案应由项目技术负责人组织编制，并经施工单位技术负责人审批签字后提交项目监理机构。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]