[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109132":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109132,783,1,"单选题","承包单位提出的技术修改要求，经相关各方同意签字后，由( )组织实施。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计代表",false,{"key":16,"text":17,"correct":14},"B","承包单位技术负责人",{"key":19,"text":20,"correct":21},"C","总监理工程师",true,{"key":23,"text":24,"correct":14},"D","专业监理工程师","2020版教材P144-145 施工单位提出的工程变更，当为要求进行某些材料\u002F工艺\u002F技术方面的技术修改时，即根据施工现场具体条件和自身的技术、经验和施工设备等，在不改变原设计文件原则的前提下，提出的对设计图纸和技术文件的某些技术上的修改要求，例如，对某种规格的钢筋采用替代规格的钢筋、对基坑开挖边坡的修改等。应在工程变更单及其附件中说明要求修改的内容及原因或理由，并附上有关文件和相应图纸。经各方同意签字后，由总监理工程师组织实施。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]