[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109120":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109120,783,1,"单选题","一般情况下，施工单位提出工程变更的情形不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","图纸出现缺陷无法施工",false,{"key":16,"text":17,"correct":14},"B","图纸不便施工，变更后更经济、方便",{"key":19,"text":20,"correct":14},"C","采用“四新”的需要",{"key":22,"text":23,"correct":24},"D","方案阶段考虑不周",true,"2020版教材P144-145 本题考查的是工程变更的控制。施工单位提出工程变更的情形一般有： (1)图纸出现错、漏、碰、缺等缺陷而无法施工； (2)图纸不便施工，变更后更经济、方便； (3)采用新材料、新产品、新工艺、新技术的需要； (4)施工单位考虑自身利益，为费用索赔而提出工程变更。 选项D属于建设单位提出工程变更的原因。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]