[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109118":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109118,783,1,"单选题","由建设单位采购的主要设备由（ ）进行开箱检查，并由三方在开箱检查记录上签字。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","勘察单位、设计单位、建设单位",false,{"key":16,"text":17,"correct":14},"B","设计单位、建设单位、施工单位",{"key":19,"text":20,"correct":14},"C","施工单位、供货单位、项目监理机构",{"key":22,"text":23,"correct":24},"D","建设单位、施工单位、项目监理机构",true,"2020版教材P112-119 本题考查的是现场施工准备质量控制。由建设单位采购的主要设备由建设单位、施工单位、项目监理机构进行开箱检查，并由三方在开箱检查记录上签字。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]