[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109110":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109110,783,1,"单选题","对需要返工处理的质量事故，项目监理机构应要求施工单位报送（ ）和经设计等相关单位认可的处理方案，并对质量事故的处理过程进行跟踪检查。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量事故调查报告",true,{"key":16,"text":17,"correct":18},"B","质量事故书面报告",false,{"key":20,"text":21,"correct":18},"C","质量事故状况观测记录",{"key":23,"text":24,"correct":18},"D","质量事故处理依据","2020版教材P137-143 本题考查的是监理通知单、工程暂停令、工程复工令的签发。对需要返工处理或加固补强的质量事故，项目监理机构应要求施工单位报送质量事故调查报告和经设计等相关单位认可的处理方案，并对质量事故的处理过程进行跟踪检查，对处理结果进行验收。项目监理机构应及时向建设单位提交质量事故书面报告，并应将完整的质量事故处理记录整理归档。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]