[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109109":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109109,783,1,"单选题","收到施工单位报送的单位工程竣工验收报审表及相关资料后，（ ）应组织监理人员进行工程质量竣工预验收。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设单位法人代表",false,{"key":16,"text":17,"correct":14},"B","建设单位现场代表",{"key":19,"text":20,"correct":21},"C","总监理工程师",true,{"key":23,"text":24,"correct":14},"D","专业监理工程师","2020版教材P104-108 本题考查的是工程施工质量控制的工作程序。按照单位工程施工总进度计划，施工单位已完成施工合同所约定的所有工程量，并完成自检工作，工程验收资料已整理完毕，应填报单位工程竣工验收报审表，报送项目监理机构竣工验收。总监理工程师组织专业监理工程师进行竣工预验收，并签署验收意见。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]